We found 15 risks in the US 93 Wickenburg highway bid documents.

Each one could be worth a question to ADOT before bids close on December 18, 2026. Here are 3, with the clause and page.
US 93 Wickenburg highway
What we found in the
US 93 Wickenburg highway
documents
Finding

The MSE wall design summary says no underdrain is required, while Section 929 requires an underdrain system

The MSE wall design summary in the plans lists the underdrain requirement as No. Section 929 of the special provisions says that, as a minimum, an underdrain system shall be provided to lead water away from the backfill and outside the limits of the wall. A bid priced without underdrains can be held to the specification. Which one governs is worth settling with ADOT before bids close.

Plans, MSE wall design summary (p. 455) and Bid Book, Section 929 (p. 382)
Finding

Pipe 150 is 28 x 20 in the plans' pipe schedule but 24 inches with a 3.75 inch wall in the earthwork report

The plans' new-pipe schedule lists Pipe 150 at East Frontage Road station 126+87 as 28 x 20 and 81 feet long. The earthwork report lists the same pipe as 24 inches inside diameter, 3.75 inches thick and 81 feet long. Excavation, bedding, trench width and backfill depend on which pipe it is, so a question to ADOT before bids close would give every bidder one configuration to price.

Plans, new-pipe schedule, and Earthwork Report MP 189.9 to 193 (p. 42)
Finding

The existing wingwall must be supported while the box culvert is extended, with no support detail in the plans

Sheet D-2.03 shows the existing wingwall to remain and requires additional support to keep it in place during the concrete box culvert extension. The plans give no support system, capacity, layout or installation detail, so the temporary support has to be designed and priced from scratch. Asking ADOT whether a detail will be issued is worth doing before bids close.

Plans, Sheet D-2.03 (p. 89)
Book a demo

One avoided issue usually pays for the platform. Customers report a 12 to 15x return.

Over $2 billion in projects covered
Béland Lapointe logo
Groupe Malo logo
Telamont in 90 seconds

Telamont reads every document on your projects and flags the risks.

  1. Connect your projects. Drawings, specs, contracts and addenda, straight from Procore, Autodesk Construction Cloud, SharePoint, Box or Dropbox.
  2. Get the risks, with the page. Conflicts, gaps and costly obligations, each linked to the page it comes from.
  3. Assign and follow up. Your team triages each risk and gives it an owner.
  4. Stay covered as documents change. New revisions and addenda are checked as they arrive.
Book a demo

See how contractors catch risks early with Telamont

$16.4M in potential costs avoided by our customers
Who you will meet
Alexandre Knox
Alexandre Knox
Your account owner
Nathaniel Nadeau
Nathaniel Nadeau
Runs your demo

Request received

Our team will reach out shortly to plan your demo.

Prefer to pick a time yourself?

Choose a time to meet
Oops! Something went wrong while submitting the form.
Return on investment

What our customers got from Telamont

$1.4M

Of rework avoided on one customer project, after a conflict was caught before execution.

40 to 50 h

Of document review saved per project, reported by a customer.

12 to 15x

Typical return on the platform. One avoided issue usually pays for it.

A note from our co-founder

The US 93 Wickenburg Ranch Way to Vista Royale project is out for bids until December 18, 2026, with 7 public documents from ADOT. We ran Telamont on that public package to see what bidders will be working with. A few points are worth raising with ADOT before bids close, and I would be glad to walk you through all of them.

Charles Goulet
Charles Goulet, Co-founder and CEO, Telamont

Questions from teams like yours

Site engineer reviewing project documents on a tablet
Are our documents private?

Yes. Your documents are never used to train AI models, ours or our providers'. They are encrypted in transit and at rest, and each organization's data is kept separate.

Which documents does Telamont read?

Plans, specifications and special provisions, contracts, addenda, and supplemental reports such as geotechnical and hazardous materials surveys.

How long does it take to get started?

Days, not months. After the walkthrough, one onboarding meeting trains your team and connects your projects, and the first risks come back with their pages.

Does it work with our tools?

Yes. Telamont connects to Procore, Autodesk Construction Cloud, SharePoint, Box, Dropbox and Microsoft Project, and sends alerts to Teams, Slack, Outlook and iMessage.

Get a 30-minute demo of Telamont
Book a demo