Section 323113.53, paragraph 1.2 lists horizontal-slide, motor-operated gates, while the equipment articles require vertical lift gates and operators, and the drawings show a vertical lift gate elevation. The gate package to price and order depends on which one governs.
The water-line notes give two different connections: a wet tap if the building is served with sprinklers, or quarter bends and a cap under the building if there are no fire protection fixtures. The documents do not say which applies, so the tie-in method and the service outage cannot be priced from them.
Article 2.6.G of Section 323113.53 describes barbed wire arms increasing the fence height to 8 feet overall, while article 2.7.A describes three strands on slanted arms increasing the height to 8 feet 6 inches. The fence height, posts and fabric depend on which one governs.





Of rework avoided on one customer project, after a conflict was caught before execution.
Of document review saved per project, reported by a customer.
Typical return on the platform. One avoided issue usually pays for it.
The ZMP underground utilities job comes with 304 pages of specifications and 68 pages of drawings. We ran Telamont on the public package to see where the specifications and drawings still disagree. A few items are worth settling with the FAA early, and I would be glad to walk you through all of them.


Yes. Your documents are never used to train AI models, ours or our providers'. They are encrypted in transit and at rest, and each organization's data is kept separate.
Plans, specifications and special provisions, contracts, addenda, and supplemental reports such as geotechnical and hazardous materials surveys.
Days, not months. After the walkthrough, one onboarding meeting trains your team and connects your projects, and the first risks come back with their pages.
Yes. Telamont connects to Procore, Autodesk Construction Cloud, SharePoint, Box, Dropbox and Microsoft Project, and sends alerts to Teams, Slack, Outlook and iMessage.