Section 23 52 00 requires the safety relief valve piping to run to the nearest floor drain or an approved local equivalent, and sheet M-401 sends the blowdown receiver discharge to an existing floor drain or floor sink. The documents do not state the drains' size, capacity or condition, so any drain modification cannot be priced from the package.
Demolition sheet ED401 states that boiler B-10 is fed from panel 1E-29, while new work sheet E-401 reconnects it to panel 1E-23B. The raceway route and the termination depend on which panel is right.
Demolition sheet ED401 states that boiler B-9 is fed from panel 1E-27, while new work sheet E-401 reconnects it to panel 1E-23A. The raceway route and the termination depend on which panel is right.





Of rework avoided on one customer project, after a conflict was caught before execution.
Of document review saved per project, reported by a customer.
Typical return on the platform. One avoided issue usually pays for it.
The Albany boiler upgrade carries more than boilers: controls across several building systems, new switchgear and a PG&E service, all within 365 days. We ran Telamont on the public package to see where the specifications and drawings still disagree. A few items are worth settling with USDA early, and I would be glad to walk you through all of them.


Yes. Your documents are never used to train AI models, ours or our providers'. They are encrypted in transit and at rest, and each organization's data is kept separate.
Plans, specifications and special provisions, contracts, addenda, and supplemental reports such as geotechnical and hazardous materials surveys.
Days, not months. After the walkthrough, one onboarding meeting trains your team and connects your projects, and the first risks come back with their pages.
Yes. Telamont connects to Procore, Autodesk Construction Cloud, SharePoint, Box, Dropbox and Microsoft Project, and sends alerts to Teams, Slack, Outlook and iMessage.