Sheet 8 lists the 8-inch foamed asphalt treatment for 291,081 square yards, while the Sheet 10 quantity summary lists 311,297 square yards for US 83. The 20,216 square yard gap sits on the base treatment item, so the quantity to price depends on which sheet governs. That is a question for TxDOT before the letting.
Sheet 8 calculates the US 83 surface course at 66,281 tons, while the quantity summary lists 68,564 tons under Item 344-7021. The difference is 2,283 tons on the paving item, which is worth settling with TxDOT before the letting.
Sheet 8 lists Item 291-7003 asphalt binder at 2,737 tons, while Sheet 10 lists 2,927 tons for US 83. The 190 ton difference is on a material bought by the ton, so which figure governs is worth asking TxDOT before the letting.





Of rework avoided on one customer project, after a conflict was caught before execution.
Of document review saved per project, reported by a customer.
Typical return on the platform. One avoided issue usually pays for it.
The US 83 passing lanes in Runnels County go to letting on December 1, 2026. We ran Telamont on the public proposal and plans to see what bidders will be working with. A few quantity differences are worth raising with TxDOT before the letting, and I would be glad to walk you through all of them.


Yes. Your documents are never used to train AI models, ours or our providers'. They are encrypted in transit and at rest, and each organization's data is kept separate.
Plans, specifications and special provisions, contracts, addenda, and supplemental reports such as geotechnical and hazardous materials surveys.
Days, not months. After the walkthrough, one onboarding meeting trains your team and connects your projects, and the first risks come back with their pages.
Yes. Telamont connects to Procore, Autodesk Construction Cloud, SharePoint, Box, Dropbox and Microsoft Project, and sends alerts to Teams, Slack, Outlook and iMessage.