Section 02 41 19 states that hazardous materials will be removed by the Government before the start of the work, and in the same section lists hazardous materials as present in the buildings to be selectively demolished. Section 02 83 33.13 specifies lead abatement for the contractor. Demolition is either cleared by the Government or run as controlled hazardous work, and the two carry very different cost and schedule.
The flooring preparation article gives a vapor emission rate of 5 lb of water per 1,000 square feet in 24 hours, and a later line sets the moisture vapor transmission threshold for monolithic resinous flooring at 3 lb. The 3 lb limit is stricter, and a slab that passes at 5 lb can still need moisture control work to pass acceptance.
Drawing P-001 makes the contractor responsible for the cost and effort to freeze the pipe if the existing valves fail to hold. The isolation method and its duration depend on valves nobody has tested, and no quantity or change mechanism covers it.





Of rework avoided on one customer project, after a conflict was caught before execution.
Of document review saved per project, reported by a customer.
Typical return on the platform. One avoided issue usually pays for it.
The SPS renovation at the Ralph H. Johnson VA has to keep sterile processing running while the new air handler and equipment go in. We ran Telamont on the public package, the statement of work, the specifications and the drawings, to see where they still disagree. A few items are worth settling with the VA early, and I would be glad to walk your team through all of them.


Yes. Your documents are never used to train AI models, ours or our providers'. They are encrypted in transit and at rest, and each organization's data is kept separate.
Plans, specifications and special provisions, contracts, addenda, and supplemental reports such as geotechnical and hazardous materials surveys.
Days, not months. After the walkthrough, one onboarding meeting trains your team and connects your projects, and the first risks come back with their pages.
Yes. Telamont connects to Procore, Autodesk Construction Cloud, SharePoint, Box, Dropbox and Microsoft Project, and sends alerts to Teams, Slack, Outlook and iMessage.