Sheet S-1.02 lists two quantities for epoxy Item 6010602, 1,211 SY and 1,079 SY, while the bid schedule carries 1,211 SY. The sealer quantity to price and order depends on which one governs.
Item 6010602 calls for epoxy sealing of the entire bridge deck, approach slabs and anchor slabs. The bridge scope on the structural sheet lists only the bridge deck and approach slabs. Where the anchor-slab sealing is included, and in which quantity, is not stated.
The pavement markings quantity summary lists item 7080202 (yellow) at 707,998 L.FT. and item 7080201 (white) at 898,254 L.FT. The bid schedule lists 857,950 L.FT. and 1,085,694 L.FT. The marking quantity to order depends on which one governs.





Of rework avoided on one customer project, after a conflict was caught before execution.
Of document review saved per project, reported by a customer.
Typical return on the platform. One avoided issue usually pays for it.
I-10 from San Simon to the New Mexico line is a long stretch to keep consistent, with plans, special provisions and addenda behind it. We ran Telamont on the public package to see where the documents disagree. If a few items are worth settling with ADOT early, I would be glad to walk your team through them.


Yes. Your documents are never used to train AI models, ours or our providers'. They are encrypted in transit and at rest, and each organization's data is kept separate.
Plans, specifications and special provisions, contracts, addenda, and supplemental reports such as geotechnical and hazardous materials surveys.
Days, not months. After the walkthrough, one onboarding meeting trains your team and connects your projects, and the first risks come back with their pages.
Yes. Telamont connects to Procore, Autodesk Construction Cloud, SharePoint, Box, Dropbox and Microsoft Project, and sends alerts to Teams, Slack, Outlook and iMessage.