Sheet ES300 identifies the new S&C Vista switch as 12.5 kA. Section 26 13 19, paragraph 1.2, requires a 25,000 A symmetrical short-circuit rating. The switch to order depends on which one governs.
A note on the ES300 electrical plan requires the concrete pad to extend 6 inches beyond the equipment, while detail 8 on sheet EJ500 shows 4 inches. The pad to form and pour depends on which one governs.
Section 31 23 23.33 gives 1500 to 1900 kg/m3 in the submittal requirements and 1900 to 2300 kg/m3 in the mixture requirements. The mix to order depends on which range governs.





Of rework avoided on one customer project, after a conflict was caught before execution.
Of document review saved per project, reported by a customer.
Typical return on the platform. One avoided issue usually pays for it.
The Battle Creek primary distribution job brings new medium-voltage service to a hospital campus that has to stay powered the whole time. We ran Telamont on the public specifications and drawings to see what your team and your electrical crew will be working with. A few items are worth settling with the VA before the first building is cut over, and I would be glad to walk you through all of them.


Yes. Your documents are never used to train AI models, ours or our providers'. They are encrypted in transit and at rest, and each organization's data is kept separate.
Plans, specifications and special provisions, contracts, addenda, and supplemental reports such as geotechnical and hazardous materials surveys.
Days, not months. After the walkthrough, one onboarding meeting trains your team and connects your projects, and the first risks come back with their pages.
Yes. Telamont connects to Procore, Autodesk Construction Cloud, SharePoint, Box, Dropbox and Microsoft Project, and sends alerts to Teams, Slack, Outlook and iMessage.