BC(2)-21 requires 48 x 48 inch CW20-series signs in the Expressway/Freeway column. Phase 2 Sheet 1 calls for 30 x 30 inch CW20 signs. Signs bought to the plan may not meet the standard at acceptance.
Sheet 162 requires removal and capping of the existing irrigation system. The proposal lists item 496-7019 only as retaining wall removal, so no bid item covers the irrigation work and no extent is stated.
Sheet 310 requires temporary sidewalk work, passing areas and protective fencing. It leaves the route location to the Engineer and gives no bid length or area.





Of rework avoided on one customer project, after a conflict was caught before execution.
Of document review saved per project, reported by a customer.
Typical return on the platform. One avoided issue usually pays for it.
The US 87 job in Victoria packs sidewalks, curb ramps and signal work into 255 working days. We ran Telamont on the public TxDOT package to see what your team will be working with. A few points are worth settling with the district early, and I would be glad to walk you through all of them.


Yes. Your documents are never used to train AI models, ours or our providers'. They are encrypted in transit and at rest, and each organization's data is kept separate.
Plans, specifications and special provisions, contracts, addenda, and supplemental reports such as geotechnical and hazardous materials surveys.
Days, not months. After the walkthrough, one onboarding meeting trains your team and connects your projects, and the first risks come back with their pages.
Yes. Telamont connects to Procore, Autodesk Construction Cloud, SharePoint, Box, Dropbox and Microsoft Project, and sends alerts to Teams, Slack, Outlook and iMessage.